draft-ietf-sfc-nsh-ecn-support
Request | Review of | draft-ietf-sfc-nsh-ecn-support |
---|---|---|
Requested revision | No specific revision (document currently at 13) | |
Type | Early Review | |
Team | Transport Area Review Team (tsvart) | |
Deadline | 2021-11-19 | |
Requested | 2021-02-25 | |
Requested by | Wesley Eddy | |
Authors | Donald E. Eastlake 3rd , Bob Briscoe , Shunwan Zhuang , Andrew G. Malis , Xinpeng Wei | |
I-D last updated | 2024-04-15 | |
IESG document state | I-D Exists | |
Completed reviews |
Tsvart Early review of -08
by Olivier Bonaventure
(diff)
|
|
Comments |
Ideally this could have a TSVART review in conjunction with the SFC WGLC. |
|
Assignment | Reviewer | Olivier Bonaventure |
State | Completed | |
Review |
review-ietf-sfc-nsh-ecn-support-08-tsvart-early-bonaventure-2021-11-19
|
|
Posted at | https://mailarchive.ietf.org/arch/msg/tsv-art/eIifhiyHjK_Fm4ls1w8LYSC9GGk | |
Reviewed revision | 08 (document currently at 13) | |
Result | Almost ready | |
Completed | 2021-11-19 |
History
Date | By | Description |
---|---|---|
2021-11-19 | Olivier Bonaventure | Request for Early review by TSVART Completed: Almost Ready. Reviewer: Olivier Bonaventure. |
2021-11-02 | Olivier Bonaventure | Assignment for Olivier Bonaventure accepted |
2021-10-27 | Magnus Westerlund | Request for Early review by TSVART is assigned to Olivier Bonaventure |
2021-02-25 | Wesley Eddy | Requested Early review by TSVART |