Abstract
An operational forwarding device may need to be re-started
(automatically or manually) for a variety of reasons, an event that
we call a "reset" in this document. Since there may be an
interruption in the forwarding operation during a reset, it is
useful to know how long a device takes to begin forwarding packets
again.
This document specifies a methodology for characterizing reset
during benchmarking of forwarding devices, and provides clarity and
consistency in reset test procedures beyond what's specified in
RFC2544. It therefore updates RFC2544.
Status of this Memo
This Internet-Draft is submitted in full conformance with the
provisions of BCP 78 and BCP 79.
Internet-Drafts are working documents of the Internet Engineering
Task Force (IETF), its areas, and its working groups. Note that
other groups may also distribute working documents as Internet-
Drafts.
Internet-Drafts are draft documents valid for a maximum of six
months and may be updated, replaced, or obsoleted by other documents
at any time. It is inappropriate to use Internet-Drafts as
reference material or to cite them other than as "work in progress."
Asati, et al. Expires January 9, 2011 [Page 1]
Internet-Draft Reset Characterization July 2010
The list of current Internet-Drafts can be accessed at
http://www.ietf.org/ietf/1id-abstracts.txt
The list of Internet-Draft Shadow Directories can be accessed at
http://www.ietf.org/shadow.html
This Internet-Draft will expire on January 9, 2011.
Copyright Notice
Copyright (c) 2010 IETF Trust and the persons identified as the
document authors. All rights reserved.
This document is subject to BCP 78 and the IETF Trust's Legal
Provisions Relating to IETF Documents
(http://trustee.ietf.org/license-info) in effect on the date of
publication of this document. Please review these documents
carefully, as they describe your rights and restrictions with
respect to this document. Code Components extracted from this
document must include Simplified BSD License text as described in
Section 4.e of the Trust Legal Provisions and are provided without
warranty as described in the Simplified BSD License.
Asati, et al. Expires January 9, 2011 [Page 2]
Internet-Draft Reset Characterization July 2010
Table of Contents
1. Introduction...................................................4
1.1. Scope.....................................................4
2. Key Words to Reflect Requirements..............................4
3. Test Requirements..............................................5
4. Reset Test.....................................................6
4.1. Hardware Reset............................................6
4.1.1. Routing Processor (RP) / Routing Engine reset........7
4.1.1.1. RP Reset for a single-RP device (REQUIRED)......7
4.1.1.2. RP Switchover for a multiple-RP device (OPTIONAL)
.........................................................9
4.1.2. Line Card (LC) Removal and Insertion (REQUIRED).....11
4.2. Software Reset...........................................13
4.2.1. Operating System (OS) reset (REQUIRED)..............13
4.2.2. Process reset (OPTIONAL)............................15
4.3. Power interruption.......................................17
4.3.1. Power Interruption (REQUIRED).......................17
5. Security Considerations.......................................19
6. IANA Considerations...........................................20
7. Acknowledgments...............................................20
8. References....................................................21
8.1. Normative References.....................................21
8.2. Informative References...................................21
Authors' Addresses...............................................22
Asati, et al. Expires January 9, 2011 [Page 3]
Internet-Draft Reset Characterization July 2010
1. Introduction
An operational forwarding device (or one of its components) may need
to be re-started for a variety of reasons, an event that we call a
"reset" in this draft. Since there may be an interruption in the
forwarding operation during a reset, it is useful to know how long a
device takes to begin forwarding packets again.
However, the answer to this question is no longer simple and
straight-forward as the modern forwarding devices employ many
hardware advancements (distributed forwarding, etc.) and software
advancements (graceful restart, etc.) that influence the recovery
time after the reset.
1.1. Scope
This document specifies a methodology for characterizing reset
during benchmarking of forwarding devices, and provides clarity and
consistency in reset procedures beyond what is specified in
[RFC2544]. These procedures may be used by other benchmarking
documents such as [RFC2544], [RFC5180], [RFC5695], etc.
This document updates Section 26.6 of [RFC2544].
This document focuses on only the reset criterion of benchmarking,
and presumes that it would be beneficial to [RFC5180], [RFC5695],
and other BMWG benchmarking efforts.
2. Key Words to Reflect Requirements
The key words "MUST", "MUST NOT", "REQUIRED", "SHALL", "SHALL NOT",
"SHOULD", "SHOULD NOT", "RECOMMENDED", "MAY", and "OPTIONAL" in this
document are to be interpreted as described in BCP 14, RFC 2119
[RFC2119]. RFC 2119 defines the use of these key words to help make
the intent of standards track documents as clear as possible. While
this document uses these keywords, this document is not a standards
track document.
Asati, et al. Expires January 9, 2011 [Page 4]
Internet-Draft Reset Characterization July 2010
3. Test Requirements
In order to provide consistent and fairness while benchmarking a set
of different DUTs, the Network tester / Operator MUST (a) use
identical control and data plane information during testing, (b)
document & report any factors that may influence the overall time
after reset / convergence.
Some of these factors include:
1. Type of reset - Hardware (line-card crash, etc.) vs. Software
(protocol reset, process crash, etc.) or even complete power
failures
2. Manual vs. Automatic reset
3. Scheduled vs. non-scheduled reset
4. Local vs. Remote reset
5. Scale - Number of line cards present vs. in-use
6. Scale - Number of physical and logical interfaces
7. Scale - Number of routing protocol instances
8. Scale - Number of Routing Table entries
9. Scale - Number of Route Processors available
10. Performance - Redundancy strategy deployed for route
processors and line cards
11. Performance - Interface encapsulation as well as achievable
Throughput [RFC2544]
12. Any other internal or external factor that may influence
recovery time after a hardware or software reset
After the tests are run, one of the characterization results
reported is the recovery time. While the recovery time during a
reset test event may be zero, there may still be effects on traffic,
such as transient delay variation or increased latency. However,
that is not covered and deemed outside the scope of this document.
In this case, only "no loss" is reported.
Asati, et al. Expires January 9, 2011 [Page 5]
Internet-Draft Reset Characterization July 2010
4. Reset Test
This section contains the description of the tests that are related
to the characterization of the time needed for DUTs (Device Under
Test) / SUTs (System Under Test) to recover from a reset. There are
three types of reset considered in this document:
1. Hardware resets
2. Software resets
3. Power interruption
Different types of reset have potentially different impact on the
forwarding behavior of the device. As an example, a software reset
(of a routing process) might not result in forwarding interruption,
whereas a hardware reset (of a line card) most likely will.
Section 4.1 describes various hardware resets, whereas Section 4.2
describes various software resets. Additionally, Section 4.3
describes power interruption tests. These sections define and
characterize these resets.
Additionally, since device specific implementations may vary for
hardware and software type resets, it is desirable to classify each
test case as "REQUIRED" or "OPTIONAL".
4.1. Hardware Reset
A test designed to characterize the time it takes a DUT to recover
from the hardware reset.
A "hardware reset" generally involves the re-initialization of one
or more physical components in the DUT, but not the entire DUT.
A hardware reset is executed by the operator for example by physical
removal of a physical component, by pressing on a "reset" button for
the component, or could even be triggered from the command line
interface.
For routers that do not contain separate Routing Processor and Line
Card modules, the hardware reset tests are not performed since they
Asati, et al. Expires January 9, 2011 [Page 6]
Internet-Draft Reset Characterization July 2010
are not relevant; instead, the power interruption tests MUST be
performed (see Section 4.3) in these cases.
4.1.1. Routing Processor (RP) / Routing Engine reset
The Routing Processor (RP) is the DUT module that is primarily
concerned with Control Plane functions.
4.1.1.1. RP Reset for a single-RP device (REQUIRED)
Objective
To characterize time needed for a DUT to recover from a Route
processor hardware reset in a single RP environment.
Procedure
First, ensure that the RP is in a permanent state to which it will
return to after the reset, by performing some or all of the
following operational tasks: save the current DUT configuration,
specify boot parameters, ensure the appropriate software files are
available, or perform additional Operating System or hardware
related task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, perform the Route Processor (RP) hardware reset at this
point. This entails for example physically removing the RP to
later re-insert it, or triggering a hardware reset by other means
(e.g., command line interface, physical switch, etc.)
Finally, the characterization is completed by measuring the
complete frame loss and calculating the recovery time from the
moment the RP is re-initialized or reinserted until traffic is re-
established, by using the following equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
Asati, et al. Expires January 9, 2011 [Page 7]
Internet-Draft Reset Characterization July 2010
Reporting format
The reset results are reported in a simple statement including the
frame loss and recovery times.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
Asati, et al. Expires January 9, 2011 [Page 8]
Internet-Draft Reset Characterization July 2010
4.1.1.2. RP Switchover for a multiple-RP device (OPTIONAL)
Objective
To characterize time needed for "secondary" Route Processor
(sometimes referred to as "backup" RP) of a DUT to become active
after a "primary" (or "active") Route Processor hardware reset.
This process is often referred to as "RP Switchover". The
characterization in this test should be done for the default DUT
behavior as well as a DUT's non-default configuration that
minimizes frame loss, if exists.
Procedure
This test characterizes "RP Switchover". Many implementations
allow for optimized switchover capabilities that minimize the
downtime during the actual switchover. This test consists of two
sub-cases from a switchover characteristics standpoint: First, a
default behavior (with no switchover-specific configurations); and
potentially second, a non-default behavior with switchover
configuration to minimize frame loss. Therefore, the procedures
hereby described are executed twice, and reported separately.
First, ensure that the RPs are in a permanent state such that the
secondary will be activated to the same state as the active is, by
performing some or all of the following operational tasks: save
the current DUT configuration, specify boot parameters, ensure the
appropriate software files are available, or perform additional
Operating System or hardware related task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, perform the primary Route Processor (RP) hardware reset at
this point. This entails for example physically removing the RP,
or triggering a hardware reset by other means (e.g., command line
interface, physical switch, etc.) It is up to the Operator to
decide if the primary RP needs to be re-inserted after a grace
period or not.
Asati, et al. Expires January 9, 2011 [Page 9]
Internet-Draft Reset Characterization July 2010
Finally, the characterization is completed by measuring the
complete frame loss and calculating the recovery time from the
moment the active RP is hardware-reset until traffic is re-
established, by using the following equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
Reporting format
The reset results are potentially reported twice, one for the
default switchover behavior (i.e., the DUT without any switchover-
specific enhanced configuration) and the other for the switchover-
specific behavior if it exists (i.e., the DUT configured for
optimized switchover capabilities that minimize the downtime
during the actual switchover). For each, the report consists of a
simple statement including the frame loss and recovery times, as
well as any specific redundancy scheme in place.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Asati, et al. Expires January 9, 2011 [Page 10]
Internet-Draft Reset Characterization July 2010
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
4.1.2. Line Card (LC) Removal and Insertion (REQUIRED)
The Line Card (LC) is the DUT component that is responsible with
packet forwarding.
Objective
To characterize time needed for a DUT to recover from a Line Card
removal and insertion event.
Procedure
For this test, the Line Card that is being hardware-reset MUST be
on the forwarding path and all destinations MUST be directly
connected.
First, complete some or all of the following operational tasks:
save the current DUT configuration, specify boot parameters,
ensure the appropriate software files are available, or perform
additional Operating System or hardware related task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, perform the Line Card (LC) hardware reset at this point.
This entails for example physically removing the LC to later re-
Asati, et al. Expires January 9, 2011 [Page 11]
Internet-Draft Reset Characterization July 2010
insert it, or triggering a hardware reset by other means (e.g.,
command line interface (CLI), physical switch, etc.). However,
most accurate results will be obtained using the CLI or a physical
switch, and therefore these are RECOMMENDED. Otherwise, the time
spent trying to physically seat the LC will get mixed into the
results.
Finally, the characterization is completed by measuring the
complete frame loss and calculating the recovery time from the
moment the LC is reinitialized or reinserted until traffic is re-
established, by using the following equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
Reporting Format
The reset results are reported in a simple statement including the
frame loss and recovery times.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Asati, et al. Expires January 9, 2011 [Page 12]
Internet-Draft Reset Characterization July 2010
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
4.2. Software Reset
To characterize time needed for a DUT to recover from the software
reset.
In contrast to a "hardware reset", a "software reset" involves only
the re-initialization of the execution, data structures, and partial
state within the software running on the DUT module(s).
A software reset is initiated for example from the DUT's Command
Line Interface (CLI).
4.2.1. Operating System (OS) reset (REQUIRED)
Objective
To characterize time needed for a DUT to recover from an Operating
System (OS) software reset.
Procedure
First, complete some or all of the following operational tasks:
save the current DUT configuration, specify software boot
parameters, ensure the appropriate software files are available,
or perform additional Operating System task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Asati, et al. Expires January 9, 2011 [Page 13]
Internet-Draft Reset Characterization July 2010
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, trigger an Operating System re-initialization in the DUT,
by operational means such as use of the DUT's Command Line
Interface (CLI) or other management interface.
Finally, the characterization is completed by measuring the
complete frame loss and calculating the recovery time from the
moment the reset instruction was given until the Operating System
finished the reload and re-initialization, inferred by the re-
establishing of traffic, by using the following equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
Reporting format
The reset results are reported in a simple statement including the
frame loss and recovery times.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Asati, et al. Expires January 9, 2011 [Page 14]
Internet-Draft Reset Characterization July 2010
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
4.2.2. Process reset (OPTIONAL)
Objective
To characterize time needed for a DUT to recover from a software
process reset.
Such time period may depend upon the number and types of process
running in the DUT and which ones are tested. Different
implementations of forwarding devices include various common
processes. A process reset should be performed only in the
processes most relevant to the tester and most impactful to
forwarding.
Procedure
First, complete some or all of the following operational tasks:
save the current DUT configuration, specify software parameters or
environmental variables, or perform additional Operating System
task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Asati, et al. Expires January 9, 2011 [Page 15]
Internet-Draft Reset Characterization July 2010
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, trigger a process reset for each process running in the DUT
and considered for testing from a management interface (e.g., by
means of the Command Line Interface (CLI), etc.)
Finally, the characterization for each individual process is
completed by measuring the complete frame loss and calculating the
recovery time from the moment the reset instruction was given
until the Operating System finished the reload and re-
initialization, inferred by the re-establishing of traffic, by
using the following equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
Reporting format
The reset results are reported in a simple statement including the
frame loss and recovery times for each process running in the DUT
and tested. Given the implementation nature of this test, details
of the actual process tested should be included along with the
statement.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Asati, et al. Expires January 9, 2011 [Page 16]
Internet-Draft Reset Characterization July 2010
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
4.3. Power interruption
"Power interruption" refers to the complete loss of power on the
DUT. It can be viewed as a special case of a hardware reset,
triggered by the loss of the power supply to the DUT or its
components, and is characterized by the re-initialization of all
hardware and software in the DUT.
4.3.1. Power Interruption (REQUIRED)
Objective
To characterize time needed for a DUT to recover efrom a complete
loss of electric power or complete power interruption. This test
simulates a complete power failure or outage, and should be
indicative of the DUT/SUTs behavior during such event.
Procedure
First, ensure that the entire DUT is at a permanent state to which
it will return to after the power interruption, by performing some
Asati, et al. Expires January 9, 2011 [Page 17]
Internet-Draft Reset Characterization July 2010
or all of the following operational tasks: save the current DUT
configuration, specify boot parameters, ensure the appropriate
software files are available, or perform additional Operating
System or hardware related task.
Second, ensure that the DUT is able to forward the traffic for at
least 15 seconds before any test activities are performed. The
traffic should use the minimum frame size possible on the media
used in the testing and rate should be sufficient for the DUT to
attain the maximum forwarding throughput. This enables a finer
granularity in the recovery time measurement.
Modern traffic generators support the feature of transmitting
packets while ignoring the link status. The operator / tester MUST
ensure that this feature is enabled.
Third, interrupt the power (AC or DC) that feeds the corresponding
DUTs power supplies at this point. This entails for example
physically removing the power supplies in the DUT to later re-
insert them, or simply disconnecting or switching off their power
feeds (AC or DC as applicable). The actual power interruption
should last at least 15 seconds.
Finally, the characterization is completed by measuring the
complete frame loss and calculating the recovery time from the
moment the power is restored or the power supplies reinserted in
the DUT until traffic is re-established, by using the following
equation:
Recovery_time = Packet_loss (packets)/Offered_rate (packets per
second).
For easier comparison with other testing, the 15 seconds are
removed from the reported recovery time.
Reporting format
The reset results are reported in a simple statement including the
frame loss and recovery times.
For each test case, it is RECOMMENDED that the following
parameters be reported in these units:
Parameter Units or Examples
Throughput Frames per second and bits per
second
Asati, et al. Expires January 9, 2011 [Page 18]
Internet-Draft Reset Characterization July 2010
Loss (average) Frames
Time (average) Seconds, all significant digits and
at least two digits variable over
the trials
Number of trials Integer count
Protocol IPv4, IPv6, MPLS, etc.
Frame Size Octets
Port Media Ethernet, GigE (Gigabit Ethernet),
POS (Packet over SONET), etc.
Port Speed 10 Gbps, 1 Gbps, 100 Mbps, etc.
Interface Encap. Ethernet, Ethernet VLAN,
PPP, HDLC, etc.
Additionally, the DUT and test bed provisioning, configuration,
and deployed methodologies that may influence the overall recovery
time MUST be listed. (Refer to the additional factors listed in
Section 3).
The reporting of results MUST regard repeatability considerations
from Section 4 of [RFC2544]. It is RECOMMENDED to perform multiple
trials and report average results.
5. Security Considerations
Benchmarking activities, as described in this memo, are limited to
technology characterization using controlled stimuli in a laboratory
environment, with dedicated address space and the constraints
specified in the sections above.
The benchmarking network topology will be an independent test setup
and MUST NOT be connected to devices that may forward the test
traffic into a production network or misroute traffic to the test
management network.
Asati, et al. Expires January 9, 2011 [Page 19]
Internet-Draft Reset Characterization July 2010
Furthermore, benchmarking is performed on a "black-box" basis,
relying solely on measurements observable external to the DUT/SUT.
Special capabilities SHOULD NOT exist in the DUT/SUT specifically
for benchmarking purposes. Any implications for network security
arising from the DUT/SUT SHOULD be identical in the lab and in
production networks.
There are no specific security considerations within the scope of
this document.
6. IANA Considerations
There is no IANA consideration for this document.
7. Acknowledgments
The authors would like to thank Ron Bonica, who motivated us to
write this document. The authors would also like to thank Al Morton,
Andrew Yourtchenko, David Newman, and John E Dawson for providing
thorough review, useful suggestions, and valuable input.
This document was prepared using 2-Word-v2.0.template.dot.
Asati, et al. Expires January 9, 2011 [Page 20]
Internet-Draft Reset Characterization July 2010
8. References
8.1. Normative References
[RFC2119] Bradner, S., "Key words for use in RFCs to Indicate
Requirement Levels", BCP 14, RFC 2119, March 1997.
[RFC2544] Bradner, S. and McQuaid, J., "Benchmarking Methodology for
Network Interconnect Devices", RFC 2544, March 1999.
8.2. Informative References
[RFC5180] Popoviciu, C., et al, "IPv6 Benchmarking Methodology for
Network Interconnect Devices", RFC 5180, May 2008.
[RFC5695] Akhter, A., Asati, R., and C. Pignataro, "MPLS Forwarding
Benchmarking Methodology for IP Flows", RFC 5695, November
2009.
Asati, et al. Expires January 9, 2011 [Page 21]
Internet-Draft Reset Characterization July 2010
Authors' Addresses
Rajiv Asati
Cisco Systems
7025-6 Kit Creek Road
RTP, NC 27709
USA
Email: rajiva@cisco.com
Carlos Pignataro
Cisco Systems
7200-12 Kit Creek Road
RTP, NC 27709
USA
Email: cpignata@cisco.com
Fernando Calabria
Cisco Systems
7200-12 Kit Creek Road
RTP, NC 27709
USA
Email: fcalabri@cisco.com
Cesar Olvera
Consulintel
Joaquin Turina, 2
Pozuelo de Alarcon, Madrid, E-28224
Spain
Phone: +34 91 151 81 99
Email: cesar.olvera@consulintel.es
Asati, et al. Expires January 9, 2011 [Page 22]