Telechat Review of draft-ietf-storm-iscsimib-04
review-ietf-storm-iscsimib-04-genart-telechat-romascanu-2013-08-25-00
Request | Review of | draft-ietf-storm-iscsimib |
---|---|---|
Requested revision | No specific revision (document currently at 04) | |
Type | Telechat Review | |
Team | General Area Review Team (Gen-ART) (genart) | |
Deadline | 2013-08-27 | |
Requested | 2013-08-08 | |
Authors | Mark Bakke , Prakash Venkatesen | |
I-D last updated | 2013-08-25 | |
Completed reviews |
Genart Last Call review of -03
by Dan Romascanu
(diff)
Genart Telechat review of -04 by Dan Romascanu Secdir Last Call review of -03 by Joseph A. Salowey (diff) |
|
Assignment | Reviewer | Dan Romascanu |
State | Completed | |
Request | Telechat review on draft-ietf-storm-iscsimib by General Area Review Team (Gen-ART) Assigned | |
Reviewed revision | 04 | |
Result | Ready | |
Completed | 2013-08-25 |
review-ietf-storm-iscsimib-04-genart-telechat-romascanu-2013-08-25-00
I am the assigned Gen-ART reviewer for this draft. For background on Gen-ART, please see the FAQ at < http://wiki.tools.ietf.org/area/gen/trac/wiki/GenArtfaq>. Please wait for direction from your document shepherd or AD before posting a new version of the draft. Document: draft-ietf-storm-iscsimib-04.txt Reviewer: Dan Romascanu Review Date: 8/25/13 IETF LC End Date: 1/28/13 IESG Telechat date: 8/29/13 Summary: Ready - All issues raised in the IETF LC review were addressed. Thanks to the authors for the responsiveness and cooperation. Major issues: Minor issues: Nits/editorial comments: