            Provisional Diameter Command Codes for 3GPP Release 5


Status of this Memo

   This document is an Internet-Draft and is in full conformance with
   all provisions of Section 10 of RFC2026 [1].

   Internet-Drafts are working documents of the Internet Engineering
   Task Force (IETF), its areas, and its working groups.  Note that
   other groups may also distribute working documents as Internet-
   Drafts.

   Internet-Drafts are draft documents valid for a maximum of six months
   and may be updated, replaced, or obsoleted by other documents at any
   time.  It is inappropriate to use Internet-Drafts as reference
   material or to cite them other than as "work in progress."

   The list of current Internet-Drafts can be accessed at
        http://www.ietf.org/ietf/1id-abstracts.txt
   The list of Internet-Draft Shadow Directories can be accessed at
        http://www.ietf.org/shadow.html.



Abstract

   This document authorizes IANA to allocate a block of Diameter command
   codes for the Third Generation Partnership Project Release 5.  This
   document does not pass judgment on the usage of these command codes.
   Further more, these command codes are for use for Release 5.  For
   future releases, these codes cannot be reused, but must be allocated
   according to the Diameter Base specification.












Loughney                 Expires - April 2003                 [Page 1]


           Provisional Diameter Command Codes for 3GPP Release 5


Table of Contents

   1. Introduction...................................................3
      1.1 Conventions used in this document..........................3
      1.2 Abbreviations..............................................3
   2. Command Code Allocation........................................3
   3. Security Consideration.........................................3
   4. References.....................................................3
   5. Acknowledgments................................................4
   6. Author's Addresses.............................................4









































Loughney                 Expires - April 2003                 [Page 2]


           Provisional Diameter Command Codes for 3GPP Release 5



1. Introduction

   The Third Generation Partnership Project (3GPP) is defining the
   Internet Multimedia Subsystem (IMS) as part of their Release 5
   architecture.  As part of this architecture, they have defined a
   Diameter application [29.229] and [29.329] which requires the use of
   new Diameter command codes [DIAM].

1.1 Conventions used in this document

   The key words "MUST", "MUST NOT", "REQUIRED", "SHALL", "SHALL NOT",
   "SHOULD", "SHOULD NOT", "RECOMMENDED",  "MAY", and "OPTIONAL" in this
   document are to be interpreted as described in RFC-2119 [2119].

1.2 Abbreviations

   3GPP  Third Generation Partnership Project

   IANA  Internet Assigned Name Authority

   IMS   Internet Multimedia Subsystem


2. Command Code Allocation

   This document authorizes IANA to allocate Diameter Command Codes 300
   through 313, for use in 3GPP Release 5. The protocols defined by
   these command codes have not been carefully reviewed by the IETF
   community and are not considered to be general mechanisms appropriate
   for broad usage. More work is needed to develop general mechanisms
   and may become a work item of an IETF Working Group. These command
   codes are intended to be used for 3GPP Release 5 only [29.228],
   [29.229].  Future 3GPP releases are expected to make use of alternate
   mechanisms.

   Command codes for 3GPP Release 6 to be allocated from the standard
   command space, with IETF documentation. The current intent as agreed
   with 3GPP is to develop a standards track application addressing the
   needs of AAA for SIP/SDP and encompassing the requirements of the
   cellular community.

3. Security Consideration

   This document does not impact the security of the Internet.


4. References



Loughney                 Expires - April 2003                 [Page 3]


           Provisional Diameter Command Codes for 3GPP Release 5


4.1 Non-Normative References

   [2026]  Bradner, S., "The Internet Standards Process -- Revision 3",
           BCP 9, RFC 2026, October 1996.


   [29.229]            3GPP TS 29.229 V5.1.0 (2002-09); Technical Specification;
           Technical Specification Group Core Network; Cx and Dx
           interfaces based on the Diameter protocol; Protocol details;
           (Release 5).

   [29.329]            3GPP TS 29.329 V5.1.0 (2002-09); Technical Specification;
           3rd Generation Partnership Project; Technical Specification
           Group Core Network; Sh Interface based on the Diameter
           protocol; Protocol details; (Release 5)

   [DIAM]  Calhoun, P., et. al., "Diameter Base Protocol",
           IETF work in progress.

4.2 Non-Normative References

   [2026]  Bradner, S., "The Internet Standards Process -- Revision 3",
           BCP 9, RFC 2026, October 1996.


5. Acknowledgments

   The author would like to thank Bernard Aboba, Randy Bush, Allison
   Mankin and Stephen Hayes.


6. Author's Addresses

   John Loughney
   Nokia
   It„merenkatu 11-13
   00180 Helsinki
   Finland
   Email: john.Loughney@Nokia.com

7. Notices

   The IETF takes no position regarding the validity or scope of any
   intellectual property or other rights that might be claimed to
   pertain to the implementation or use of the technology described in
   this document or the extent to which any license under such rights
   might or might not be available; neither does it represent that it
   has made any effort to identify any such rights.  Information on the
   IETF's procedures with respect to rights in standards-track and


Loughney                 Expires - April 2003                 [Page 4]


           Provisional Diameter Command Codes for 3GPP Release 5


   standards-related documentation can be found in BCP-11.  Copies of
   claims of rights made available for publication and any assurances of
   licenses to be made available, or the result of an attempt made to
   obtain a general license or permission for the use of such
   proprietary rights by implementors or users of this specification can
   be obtained from the IETF Secretariat.

   The IETF invites any interested party to bring to its attention any
   copyrights, patents or patent applications, or other proprietary
   rights, which may cover technology that may be required to practice
   this standard.  Please address the information to the IETF Executive
   Director.







































Loughney                 Expires - April 2003                 [Page 5]